Dear Neighbor,
Through the hendersonroad.com mailbox, I received an
email from Steven Ware who lives on Henderson Road. He'd observed a
survey crew working on Henderson Road during Thanksgiving week near
Cardinal Drive and Tipperary Trail. He asked if I knew why they are
surveying Henderson Road, and is there some kind of construction about to
start. Steven provided me with the company name on the trucks.
Both EES Consulting, Inc. (survey crew) and Pond & Company
(engineering consultant) have been very responsive to my calls.
Steven and I thought the Henderson Road neighborhood
probably would have the same questions as we do about the project.
I've posted our questions and responses provided by Kevin Skinner of Pond
& Company.
Both sides. In locations
where sidewalk already exists, it will be maintained and not replaced.
It depends on many
factors. The engineering design is not complete yet. If additional
property is needed beyond the county right of way, county representatives
will meet with owners to purchase this property. They can answer specific
questions about setbacks, shrubs, fences, hill slopes, etc. at that time.
Once the preliminary design is complete, the plans will available for
review at DeKalb County Engineering offices.
This depends on the
specific conditions related to each parcel. This project will require some
clearing of trees and shrubbery, but clearing will be kept to a minimum.
Generally, the curb &
gutter and related storm drain piping system will eliminate the need for
drainage ditches. Some ditches may remain and this will be determined
during engineering design.
Each driveway affected
will be replaced in kind, concrete for concrete, asphalt for asphalt. The
county will work with owners in special circumstances. If
a drainage ditch is maintained, the pipe under the driveway will be
maintained or replaced.
Access to residences will
be maintained during the construction process. If necessary,
reconstruction of driveway entrances will be coordinated with the
residents.
Mailboxes will be moved
to either the buffer strip between the curb and sidewalk, or behind the
sidewalk depending on the specific conditions related to each location.
Two lanes of traffic will
remain open during construction. If temporary closure of a travel lane is
required, a reasonable time of day will be chosen, and signage or flagmen
will be utilized.
The project was selected
for funding by the DeKalb County Board of Commissioners.
The project is being
sponsored by DeKalb County. The construction will be paid for by a
combination of Federal and County funds.
This project is scheduled
to begin construction in 2009. The Henderson Road corridor is only one
part of this three-part project. The other corridors are Flat Shoals Road
and Salem Road. The entire project is estimated to take 12 months to
complete. The timetable to begin construction and the duration of
construction are subject to change as more detailed designs are developed.
Contact the Engineering
Consultant, Kevin Skinner of Pond & Company at 678.336.7740 for more
information.
The proposed curb &
gutter is 30" wide (24" gutter, 6" curb). A 2' grass strip is proposed
between the curb and the 5' wide sidewalk.
When construction beings,
the contractor will install work zone signs in the vicinity. County
representatives will contact property owners directly to discuss the
purchase of any property that is needed for this project.
There is not a project
website, but residents can contact Kevin Skinner of Pond & Company
at 678.336.7740 for more information.
Sources: Steven Ware, Kevin Skinner, Jenni
Wasmer
The
project is moving along, but we are still a long way from
construction. I will keep you informed when we reach milestones. I am
as anxious as anyone, so we're doing everything we can.
Some general advice I could give is for people to
make sure to locate their landscaping off the county right of way. Each
person should have a survey of their property and usually the property
map will have the county right of way line. If the county is impacting
landscaping, fences, trees, etc. within a property, the county will
negotiate terms with the owner on a case by case basis.
We
are more than halfway done with the plans (keep in mind there are 3
corridors for this contract). Once the design is nearly done,
county officials will need to meet with each and every owner on
Henderson where additional right of way is required. This is a
long process. Since there are 3 corridors, it could take a year or
two. The project is not let for construction until all the required
property is acquired. So unfortunately, we are still a few years
away from construction.
About hendersonroad.com
To respect your email address
privacy, the recipients received this email via blind courtesy copy
(bcc). Email addresses were provided by residents interested in staying
informed of important community news, crime prevention alerts, and recent
updates to
hendersonroad.com.
Subscribe/Unsubscribe:
Click here.
The mailbox is checked daily.
** Please consider my forwarding of this information as a means to keep
the Henderson Road neighborhood informed. **
Regards,
Jenni, Website Coordinator